Schedule

Clearly, the project schedule deserves its own page. So here it is.

 

Year 2016

Design and planning

  • February 1 – Initial meeting with architect
  • February 15 – Executed contract with architect
  • February 29 – Reviewed initial architectural plans (separate guest room above garage)
  • March 2 –  Meeting with architect
  • April 7 – Review second draft conceptual plan
  • May 25 – Apply for site variance
  • May 30 – Floor Plan revisions from architect

Permitting and Loan

  • June 23 –  Zoning Board hearing on site variance
  • August 20 – Began construction loan application process
  • August 30 – Conceptual estimate from builder
  • September 2 – Executed contract with builder
  • September 16 – Geotech report completed
  • September 28 – Elevation certificate completed
  • October 28 – Building permit issued
  • November 1 – Demo permit issued
  • November 7 – Closed on construction loan

Construction

  • November 18 – Demo begins
  • November 25 – Excavation for foundation
  • December 15 – Foundation forms set
  • December 19 – Forms Survey Completed

Year 2017

  • February 16 – Foundation Poured
  • March 14 – Framing Starts
  • March 24 – Exterior Vapor Barrier
  • April 7 – Board and Batten Siding, Windows and Roof Sub-base
  • April 26 – Exterior Paint
  • May 15 – Plumbing
  • May 30 – Electrical
  • June 10 – Insulation
  • June 24 – Sheetrock started
  • June 29 – Cabients
  • July 1 – Brick and Chimney
  • July 15 – Interior Doors
  • July 22 – Wood trim
  • July 30 – Interior Paint – First Coats
  • August 5 – Counter-tops and Cabinet doors
  • September  2 – Gas meter hooked up
  • September 2 – Interior light fixtures installed, tile flooring
  • September 7 – Tile complete, baths and kitchen; Trenched for Underground Electrical Conduit
  • September 16 – Front Walk and Driveway formed and rebar installed
  • September 21 – Poured Concrete – Front Walk and Driveway; Interior Flooring completed
  • September 23 – A/C Units set outside
  • September 30 – Shower Glass Installed
  • October 7 – Building Fire Pit
  • October 14 – Fence Built; Vent Hood Installed
  • October 17 – Landscaping started – River rock for side yards
  • October 23 – Electrical Finally Connected
  • October 25 – New Front Door Installed
  • October 28 – Cable Installed
  • November 3 – Set up Pumice Rock in Fire Pit