Clearly, the project schedule deserves its own page. So here it is.
Year 2016
Design and planning
- February 1 – Initial meeting with architect
- February 15 – Executed contract with architect
- February 29 – Reviewed initial architectural plans (separate guest room above garage)
- March 2 – Meeting with architect
- April 7 – Review second draft conceptual plan
- May 25 – Apply for site variance
- May 30 – Floor Plan revisions from architect
Permitting and Loan
- June 23 – Zoning Board hearing on site variance
- August 20 – Began construction loan application process
- August 30 – Conceptual estimate from builder
- September 2 – Executed contract with builder
- September 16 – Geotech report completed
- September 28 – Elevation certificate completed
- October 28 – Building permit issued
- November 1 – Demo permit issued
- November 7 – Closed on construction loan
Construction
- November 18 – Demo begins
- November 25 – Excavation for foundation
- December 15 – Foundation forms set
- December 19 – Forms Survey Completed
Year 2017
- February 16 – Foundation Poured
- March 14 – Framing Starts
- March 24 – Exterior Vapor Barrier
- April 7 – Board and Batten Siding, Windows and Roof Sub-base
- April 26 – Exterior Paint
- May 15 – Plumbing
- May 30 – Electrical
- June 10 – Insulation
- June 24 – Sheetrock started
- June 29 – Cabients
- July 1 – Brick and Chimney
- July 15 – Interior Doors
- July 22 – Wood trim
- July 30 – Interior Paint – First Coats
- August 5 – Counter-tops and Cabinet doors
- September 2 – Gas meter hooked up
- September 2 – Interior light fixtures installed, tile flooring
- September 7 – Tile complete, baths and kitchen; Trenched for Underground Electrical Conduit
- September 16 – Front Walk and Driveway formed and rebar installed
- September 21 – Poured Concrete – Front Walk and Driveway; Interior Flooring completed
- September 23 – A/C Units set outside
- September 30 – Shower Glass Installed
- October 7 – Building Fire Pit
- October 14 – Fence Built; Vent Hood Installed
- October 17 – Landscaping started – River rock for side yards
- October 23 – Electrical Finally Connected
- October 25 – New Front Door Installed
- October 28 – Cable Installed
- November 3 – Set up Pumice Rock in Fire Pit